Cheadle Hall Construction Projects - Replace Cooling Generating Systems, Replace Generator, Replace Terminal and Package Units

Scheduled Maintenance Report for UCSB Administrative Services

Update

Upcoming Crane Activity on Thursday, September 17, from 6:00am to 4:00pm

For public safety, all work areas will be clearly delineated and controlled throughout the activity. The contractor will also have staff on site to coordinate pedestrian and vehicle traffic and help maintain safe access around the work area.

IMPORTANT ACCESS INFORMATION:
The main doors to Cheadle Hall will NOT be accessible during the crane activity. Please plan to enter and exit the building using the WEST DOORS.

We encourage everyone who will be accessing Cheadle Hall during this time to plan accordingly and allow additional time for navigating around the controlled work areas.

Thank you in advance for your cooperation as the project team and contractor work to safely complete this activity.
Posted Sep 10, 2026 - 15:59 PDT

Update

Upcoming Electrical Shutdown - 8/15 6:00am - 5:00pm

On Saturday, August 15, from 6:00 a.m. to 5:00 p.m., there will be a scheduled electrical shutdown to support the construction projects at Cheadle Hall.

We apologize for any inconvenience this may cause and will make every effort to restore power and re-energize the electrical panels before 5:00 p.m.

Thank you for your patience and understanding.
Posted Aug 06, 2026 - 16:44 PDT

Update

Upcoming Activities:

See below the scheduled construction activities in the Cheadle Hall basement next week.

Week of 7/20

Monday - Welding/Installing pipe in basement

Tuesday - Welding/Installing pipe in basement

Wednesday - Welding/Installing pipe in basement

Thursday - Welding/Installing pipe in basement
Fan restoration in basement

Friday - Fan restoration in basement


Work will include minor demolition, partial HVAC shutdowns, and cleaning. Impacts include possible interruptions to the ventilation systems and odors. All products to be used meet the UCSB required specifications as non-toxic.
Posted Jul 17, 2026 - 14:21 PDT

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jul 14, 2026 - 08:12 PDT

Scheduled

The Cheadle HVAC upgrade project is informing Cheadle Hall building occupants that the air conditioning system is currently under reconstruction, and not in operation at this time. Every effort is being made to expedite the work, which when complete will provide improved performance and efficiency; however, for the next several months the system will be down. With an approaching heat event, people are cautioned to take measures to ensure their safety and comfort, including appropriate dress, use of fans, and intake of water. We apologize for the inconvenience!
Posted Jul 14, 2026 - 08:11 PDT
This scheduled maintenance affects: CAMPUS BUILDINGS (Cheadle Hall - UCSB Building 552).