Life Sciences Bldg. 235 - Interruption of Ventilation, Heating, Cooling and Exhaust

Scheduled Maintenance Report for UCSB Administrative Services

Completed

The scheduled maintenance has been completed.
Posted Oct 20, 2026 - 17:00 PDT

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Oct 19, 2026 - 11:00 PDT

Scheduled

Life Sciences Bldg. 235 - Interruption of Ventilation, Heating, Cooling and Exhaust (Office Section)

Date: October 19, 2026 11:00 am to 4:00 pm
October 20, 2026 7:00 am to 4:00 pm


FM Preventative Maintenance staff will be performing scheduled maintenance work on the building’s ventilating and air conditioning (HVAC) systems.
--------------------------------------------------------------------------------------------
Monday October 19, 2026
Tuesday October 20, 2026

Supply fan S-3 will be off from 11AM to 4 pm (serves the office section, floors 1-4)

--------------------------------------------------------------------------------------------
Please contact Michael Lindner, Facilities Management Preventative Maintenance Superintendent with any questions of concerns: michael.lindner@ucsb.edu.
Posted Oct 19, 2026 - 10:26 PDT
This scheduled maintenance affected: CAMPUS BUILDINGS (Life Science - UCSB Building 235).