Planned Campus Power Outage

Scheduled Maintenance Report for UCSB Administrative Services

Completed

This is the final all-clear message. Isolated building-specific issues will be communicated via https://status.arit.ucsb.edu/.
Posted Mar 28, 2025 - 12:00 PDT

Verifying

Power service to the campus has been restored. Facilities Management will be checking system functionality at campus facilities and a final 'all clear' message will be sent when all major systems are operational.
Posted Mar 28, 2025 - 08:08 PDT

Update

The scheduled power service interruption and related infrastructure maintenance are progressing as expected. We will provide further updates as they become available. Thank you for your patience and cooperation during this essential work.
Posted Mar 28, 2025 - 01:35 PDT

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Mar 27, 2025 - 21:00 PDT

Scheduled

The Public Utilities Commission has directed Southern California Edison (SCE) to perform upgrades on the power transmission systems serving the campus. The work entails repairs on the vault located on Los Carneros Road, repairs to the Remote Transmission Switch that leads to the Colegio Substation, and a deteriorated pole replacement. This work will require a power service interruption (i.e. power outage) to the UC Santa Barbara main campus and all areas served by the campus electrical distribution system.

SCE expects their portion of the outage to be over before noon on Friday, March 28. Once power has been restored, Facilities Management will re-energize campus and check all building systems to ensure they are operating, and will provide updates via Statuspage.

For your safety, we recommend you vacate all non-residential buildings by 8 p.m. Thursday, March 27.

The planned service interruption will impact UC Santa Barbara properties and facilities only, including all main campus buildings and a number of adjacent housing and dining facilities that receive their electrical power service directly from campus.

Faculty housing in the Ocean Walk and West Campus developments are on separate circuits and will not be impacted.

A planning process is currently underway to identify and address the needs of our campus community. Please visit the Planned Power Outage webpage so you can see how to prepare your area.

https://www.energy.ucsb.edu/planned-power-outage

If you have questions or would like to identify areas that may require special attention, please email: poweroutage@fm.ucsb.edu
Posted Mar 12, 2025 - 10:29 PDT
This scheduled maintenance affected: CAMPUS BUILDINGS (Arts - UCSB Building 534, Bio Sci Instruction Facility - UCSB Building 504, BioEngineering - UCSB Building 512, Biological Sciences II - UCSB Building 571, Biology Research Lab - UCSB Bldg 569, Bren Hall - UCSB Building 521, Broida Hall - UCSB Building 572, Buchanan Hall - UCSB Building 573, Campbell Hall - UCSB Building 538, Cheadle Hall - UCSB Building 552, Chemistry - UCSB Building 557, Chemistry Annex - UCSB Building 570, CLAS - UCSB Building 300, Cloud Research Lab - UCSB Building 575, Creative Studies - UCSB Building 494, Education - UCSB Building 275, El Centro - UCSB Building 406, Elings Hall - UCSB Building 266, Ellison Hall - UCSB Building 563, Library - UCSB Building 525, Engineering II - UCSB Building 503, Engineering Science - UCSB Building 225, Environmental Health & Safety - UCSB Building 565, Events Center - UCSB Building 505, Girvetz Hall - UCSB Building 564, Harder Stadium - UCSB Building 578/580, Harold Frank Hall - UCSB Building 556, Henley Hall - UCSB Building 226, Humanities & Social Sciences - USCB Building 515, Interactive Learning Pavilion - UCSB Building 506, Intercollegiate Athletics - UCSB Building 243, Kerr Hall - UCSB Building 591, Kohn Hall - UCSB Building 567, Life Science - UCSB Building 235, Marine Biotechnology Lab - UCSB Building 555, Marine Science - UCSB Building 520, Materials Research Lab - UCSB Building 615, Mosher Alumni House - UCSB Building 517, Multi-Activity Center - UCSB Building 511, Music - UCSB Building 531, Noble Hall - UCSB Building 544, North Hall - UCSB Building 535, Old Gym and Pool - UCSB Building 479, Ocean Science Education Building - UCSB Building 514, Phelps Hall - UCSB Building 560, Physical Sciences North - UCSB Building 657, Physical Sciences South - UCSB Building 672, Pollock Theater - 277, Psychology - UCSB Building 551, Psychology East - UCSB Building 251, Public Safety - UCSB Building 574, Recreation Center - UCSB Building 516, Robertson Gym - UCSB Building 533, Social Sciences & Media Studies - UCSB Building 276, South Hall - UCSB Building 528, Storke Publications - UCSB Building 589, Student Affairs & Administrative Services - UCSB Building 568, Student Health - UCSB Building 588, Student Resource Building - UCSB Building 221, Student Services - UCSB Building 599, Theater & Dance East - UCSB Building 554, Theater & Dance West - UCSB Building 223, Webb Hall - UCSB Building 526, Woodhouse Lab - UCSB Building 546) and CAMPUS INFRASTRUCTURE (Electrical Distribution, Chilled Water Loop).