Thursday, July 9th - Panel EDP Shut Down Duration: 7:00am - 12:00pm Affected Components: Emergency outlets and emergency lighting
Posted Jul 07, 2026 - 14:25 PDT
Update
Scheduled maintenance is still in progress. We will provide updates as necessary.
Posted Jul 07, 2026 - 14:19 PDT
Update
Upcoming Activities:
Week of July 6th,
Monday – Cheadle basement hangers and pipe install
Tuesday – Cheadle Basement hangers and pipe install
Wednesday – Cheadle Basement hangers and pipe install (TBD fire hose panel mainline leak repair)
Thursday – Cheadle Basement hangers and pipe install (TBD fire hose panel mainline leak repair)
Posted Jul 02, 2026 - 15:24 PDT
Update
Ongoing Activities (Updated 6/18):
- Rebar installation at Cheadle Hall new generator location - Installation of conduit, grounding rod, and grounding cable at new generator location
Upcoming Activities:
Cheadle Hall Water Shut Down (single day activity) - Friday June 19
Concrete pour at new generator location (single day activity) - Monday June 22
Concrete cutting in Cheadle Hall basement - Monday June 22 at 8:00am Duration: Approximately 4 hours Noise Level: Loud
Large Reach Fork is arriving - Tuesday June 23 Location: North east corner of Cheadle Hall outside of stairwell Duration: Several Weeks
**PLEASE NOTE that the stairwell will remain accessible but it is recommended that building occupants use the interior stairs or the elevators to go up and down floors**
Concrete demolition in Cheadle Hall Basement - Wednesday June 24 at 6:00am - 8:00am Duration: Approximately 2 Hours Noise Level: Loud
Crane onsite - Date TBD, tentatively scheduled for the week of 6/29
Posted Jun 18, 2026 - 16:45 PDT
Update
Ongoing Activities:
- Rebar installation at Cheadle Hall new generator location - Installation of conduit, grounding rod, and grounding cable at new generator location
Upcoming Activities:
Cheadle Hall Water Shut Down (single day activity) - Friday June 19 Concrete pour at new generator location (single day activity) - Monday June 22
Concrete demo in Cheadle Hall basement - Tentatively scheduled for Tuesday June 23 Details: Start time at 5:00am, loudest activities to be completed by 6:00am
Crane onsite - Date TBD, tentatively scheduled for the week of 6/29
Posted Jun 17, 2026 - 15:59 PDT
Update
Current Activities:
Week of May 25th,
- Abatement work in the Cheadle Hall basement began on May 27 and will continue through the end of the week.
- The underground subcontractor is completing final work activities. Work is anticipated to be completed by the end of this week or early next week.
- Fencing along the walkways is scheduled to be removed next week. Fencing in the center area will remain in place for contractor laydown through project completion.
Posted May 27, 2026 - 08:19 PDT
Update
Upcoming Activities:
Week of May 11th, 2026
- Contractor will have laydown area set up in the courtyard between Cheadle Hall and Campbell Hall
- Contractor will be beginning demo work in the basement | Construction Noise: Moderate
- Contractor will be beginning demo work on the roof | Construction Noise: Moderate
- Underground subcontractor be beginning their work in the courtyard between Cheadle Hall and Campbell Hall. The underground contractor will be sequentially trenching across the plaza. Please note that the underground subcontractor's work is expected to be completed in two weeks 5/22 | Construction Noise: Moderate - Severe
Posted May 08, 2026 - 15:00 PDT
Update
Notice: Contractor Vehicle Near Cheadle Hall on 4/28
The contractor will have a truck parked adjacent to the new generator location (in the planter at the northeastern corner of Cheadle Hall) tomorrow, April 28, for approximately 2–4 hours.
The vehicle will be clearly marked and surrounded by delineators and caution tape to ensure visibility and maintain safety for all pedestrians and nearby traffic.
Please use caution when passing through the area.
Posted Apr 27, 2026 - 08:42 PDT
Update
We have our demo contractor scheduled to perform their work next Thursday and Friday, April 23 & 24. The team plans on starting at 6 AM and will be done at 2:30PM. This will most likely be louder than normal demo due to the echo chamber effect in the basement. We will do our best to get the loud work done as early as possible each day.
Posted Apr 14, 2026 - 16:22 PDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Apr 03, 2026 - 15:30 PDT
Scheduled
Design & Construction Services has three projects at Cheadle Hall with Plant Construction. See construction details below:
Work in the projects will include:
- Replacing the existing generator in the basement with a new generator in the planter area north east of Cheadle Hall.
- Removing the existing chiller and cooling tower and connecting the building to the campus chilled water loop. This will involve work in the basement, rooftop penthouse, and the installation of new underground piping across the plaza.
- Rebuilding of air handler equipment in the basement and rooftop penthouse.
Duration is anticipated to be now through late Fall. This listing will be updated throughout the project for upcoming construction activities and notifications.
Posted Apr 03, 2026 - 15:27 PDT
This scheduled maintenance affected: CAMPUS BUILDINGS (Cheadle Hall - UCSB Building 552).