We will be undergoing construction in the basement of the library, Ocean Side. Below is our current schedule of activities:

Two-day shutdown of the cooling system in Building A, beginning Monday 6/15
30-day shutdown of the cooling system in the rest of the library, beginning Monday 6/15
Chiller delivery and crane activity, Monday 6/22 through Tuesday 6/23
Ongoing concrete work, beginning Monday 6/29

Impacts include crane activity, noise, and disruption to the building's cooling system.
Posted Jun 12, 2026 - 09:23 PDT
This scheduled maintenance affects: CAMPUS INFRASTRUCTURE (Chilled Water Loop) and CAMPUS BUILDINGS (Library - UCSB Building 525).