Bldg. 266 Elings Hall - Interruption of Ventilation, Heating, Cooling

Scheduled Maintenance Report for UCSB Administrative Services

Completed

The scheduled maintenance has been completed.
Posted Oct 13, 2026 - 08:30 PDT

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Oct 13, 2026 - 07:00 PDT

Scheduled

FM Preventative Maintenance staff will be performing inspection of Clean Room Air Handler PAH-1

Tuesday Oct. 13, 2026
Clean Room Air Handler Units – PAH will be off from 7:00am to 7:30am

Please contact Michael Lindner, Facilities Management Preventative Maintenance Superintendent with any questions of concerns: michael.lindner@ucsb.edu.
Posted Oct 12, 2026 - 10:07 PDT
This scheduled maintenance affected: CAMPUS BUILDINGS (Elings Hall - UCSB Building 266).