In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jun 22, 2026 - 07:00 PDT
Scheduled - Underground utility work, including saw cutting, trenching and compaction will take place in the access drive between Kerr Hall and the Arbor beginning June 22nd for an approximate duration of two weeks. Non-emergency vehicles should avoid the area. Direct any questions on these activities to Jordan Sager, Facilities Management Associate Director, at jsager@ucsb.edu or (805) 705-5630.
Jun 22, 2026 07:00 - Jul 3, 2026 16:00 PDT
Update - Ongoing Activities (Updated 6/18):

- Rebar installation at Cheadle Hall new generator location
- Installation of conduit, grounding rod, and grounding cable at new generator location

Upcoming Activities:

Cheadle Hall Water Shut Down (single day activity) - Friday June 19

Concrete pour at new generator location (single day activity) - Monday June 22

Concrete cutting in Cheadle Hall basement - Monday June 22 at 8:00am
Duration: Approximately 4 hours
Noise Level: Loud

Large Reach Fork is arriving - Tuesday June 23
Location: North east corner of Cheadle Hall outside of stairwell
Duration: Several Weeks

**PLEASE NOTE that the stairwell will remain accessible but it is recommended that building occupants use the interior stairs or the elevators to go up and down floors**

Concrete demolition in Cheadle Hall Basement - Wednesday June 24 at 6:00am - 8:00am
Duration: Approximately 2 Hours
Noise Level: Loud

Crane onsite - Date TBD, tentatively scheduled for the week of 6/29

Jun 18, 2026 - 16:45 PDT
Update - Ongoing Activities:

- Rebar installation at Cheadle Hall new generator location
- Installation of conduit, grounding rod, and grounding cable at new generator location

Upcoming Activities:

Cheadle Hall Water Shut Down (single day activity) - Friday June 19
Concrete pour at new generator location (single day activity) - Monday June 22

Concrete demo in Cheadle Hall basement - Tentatively scheduled for Tuesday June 23
Details: Start time at 5:00am, loudest activities to be completed by 6:00am

Crane onsite - Date TBD, tentatively scheduled for the week of 6/29

Jun 17, 2026 - 15:59 PDT
Update - Current Activities:

Week of May 25th,

- Abatement work in the Cheadle Hall basement began on May 27 and will continue through the end of the week.

- The underground subcontractor is completing final work activities. Work is anticipated to be completed by the end of this week or early next week.

- Fencing along the walkways is scheduled to be removed next week. Fencing in the center area will remain in place for contractor laydown through project completion.

May 27, 2026 - 08:19 PDT
Update - Upcoming Activities:

Week of May 11th, 2026

- Contractor will have laydown area set up in the courtyard between Cheadle Hall and Campbell Hall

- Contractor will be beginning demo work in the basement | Construction Noise: Moderate

- Contractor will be beginning demo work on the roof | Construction Noise: Moderate

- Underground subcontractor be beginning their work in the courtyard between Cheadle Hall and Campbell Hall. The underground contractor will be sequentially trenching across the plaza. Please note that the underground subcontractor's work is expected to be completed in two weeks 5/22 | Construction Noise: Moderate - Severe

May 08, 2026 - 15:00 PDT
Update - Notice: Contractor Vehicle Near Cheadle Hall on 4/28

The contractor will have a truck parked adjacent to the new generator location (in the planter at the northeastern corner of Cheadle Hall) tomorrow, April 28, for approximately 2–4 hours.

The vehicle will be clearly marked and surrounded by delineators and caution tape to ensure visibility and maintain safety for all pedestrians and nearby traffic.

Please use caution when passing through the area.

Apr 27, 2026 - 08:42 PDT
Update - We have our demo contractor scheduled to perform their work next Thursday and Friday, April 23 & 24. The team plans on starting at 6 AM and will be done at 2:30PM. This will most likely be louder than normal demo due to the echo chamber effect in the basement. We will do our best to get the loud work done as early as possible each day.
Apr 14, 2026 - 16:22 PDT
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Apr 03, 2026 - 15:30 PDT
Scheduled - Design & Construction Services has three projects at Cheadle Hall with Plant Construction. See construction details below:

Work in the projects will include:

- Replacing the existing generator in the basement with a new generator in the planter area north east of Cheadle Hall.

- Removing the existing chiller and cooling tower and connecting the building to the campus chilled water loop. This will involve work in the basement, rooftop penthouse, and the installation of new underground piping across the plaza.

- Rebuilding of air handler equipment in the basement and rooftop penthouse.

Duration is anticipated to be now through late Fall. This listing will be updated throughout the project for upcoming construction activities and notifications.

Apr 3, 2026 15:30 - Sep 2, 2026 17:30 PDT
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jun 15, 2026 - 07:00 PDT
Scheduled - We will be undergoing construction in the basement of the library, Ocean Side. Below is our current schedule of activities:

Two-day shutdown of the cooling system in Building A, beginning Monday 6/15
30-day shutdown of the cooling system in the rest of the library, beginning Monday 6/15
Chiller delivery and crane activity, Monday 6/22 through Tuesday 6/23
Ongoing concrete work, beginning Monday 6/29

Impacts include crane activity, noise, and disruption to the building's cooling system.

Jun 15, 2026 07:00 - Jul 15, 2026 07:00 PDT
Identified - In anticipation of future development of the East Campus Student Housing Project, please note that a single lane for a portion of UCEN Rd will be closed to the public from 6 AM to 8 AM on Tuesday, June 16th, 2026. The map linked below will be updated to reflect this shortly.
https://www.map.ucsb.edu/?id=1982#!ce/60251?ct/90724,98591,93878,93879,96994,97031,60251?m/1212780?s/

Construction activities will center around underground utility work beneath the closed portion of the roadway for the East Campus project. Flaggers and signage will be provided during the closure to assist the public navigating this route.

Should you have any questions or concerns regarding these traffic impacts and construction work, please contact DCS Project Manager, Ana Heris at anaheris@ucsb.edu.

Jun 12, 2026 - 15:19 PDT
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
May 26, 2026 - 07:00 PDT
Scheduled - The freight elevator (Car #3) in Biological Sciences II (Bldg 571) will be out of service beginning Tuesday, May 26th through the end of August while elevator modernization work is performed.

Please plan accordingly, as freight elevator access will be unavailable during this time.

If you have any questions or concerns, please contact Perrin Pellegrin, DCS Program Manager, at (805) 570-7429 or perrin@ucsb.edu

May 26, 2026 07:00 - Aug 31, 2026 16:00 PDT
Identified - The heating system in Education (Bldg 275) is currently turned off while Facilities Management (FM) works to repair the system.

If you have any questions or concerns, please contact Mike Smiyun, FM HVAC Sr. Superintendent, at (805) 451-8990

Mar 16, 2026 - 08:45 PDT
Investigating - Service Outage Notification
Dec 13, 2025 - 08:22 PST

About This Site

Welcome to the UCSB Administrative Services Status page. This site provides timely information on resources managed by the Administrative Services Division of UCSB, including maintenance events, construction disturbances, and other service interruptions of business/IT systems and facilities. Please subscribe to email or text notifications advising when a major incident takes place or when infrastructure interruptions occur at specific UCSB facilities.

DEPARTMENTAL SYSTEMS HEALTH DASHBOARDS
----------------------------------------------------------------------------
UCSB Campus Services: http://status.ucsb.edu/
Instructional Development: http://status.id.ucsb.edu/
Student Affairs: https://status.sa.ucsb.edu/
Library: https://status.library.ucsb.edu/

CAMPUS BUILDINGS Under Maintenance
90 days ago
100.0 % uptime
Today
Arts - UCSB Building 534 Operational
Bio Sci Instruction Facility - UCSB Building 504 Operational
BioEngineering - UCSB Building 512 Operational
Biological Sciences II - UCSB Building 571 Operational
Biology Research Lab - UCSB Bldg 569 Operational
Bren Hall - UCSB Building 521 Operational
Broida Hall - UCSB Building 572 Operational
Buchanan Hall - UCSB Building 573 Operational
Building 434 - UCSB Building 434 Operational
90 days ago
100.0 % uptime
Today
Campbell Hall - UCSB Building 538 Operational
Cheadle Hall - UCSB Building 552 Under Maintenance
Chemistry - UCSB Building 557 Operational
Chemistry Annex - UCSB Building 570 Operational
CLAS - UCSB Building 300 Operational
Cloud Research Lab - UCSB Building 575 Operational
Creative Studies - UCSB Building 494 Operational
Education - UCSB Building 275 Operational
El Centro - UCSB Building 406 Operational
Elings Hall - UCSB Building 266 Operational
Ellison Hall - UCSB Building 563 Operational
Library - UCSB Building 525 Under Maintenance
Embarcadero Hall - UCSB Building 941 Operational
Engineering II - UCSB Building 503 Operational
Engineering Science - UCSB Building 225 Operational
Environmental Health & Safety - UCSB Building 565 Operational
Events Center - UCSB Building 505 Operational
Girvetz Hall - UCSB Building 564 Operational
Harder Stadium - UCSB Building 578/580 Operational
Harold Frank Hall - UCSB Building 556 Operational
Henley Hall - UCSB Building 226 Operational
Humanities & Social Sciences - USCB Building 515 Operational
Interactive Learning Pavilion - UCSB Building 506 Operational
Intercollegiate Athletics - UCSB Building 243 Operational
Isla Vista Theater - UCSB Building 948 Operational
Kerr Hall - UCSB Building 591 Under Maintenance
Kohn Hall - UCSB Building 567 Operational
Life Science - UCSB Building 235 Operational
Marine Biotechnology Lab - UCSB Building 555 Operational
Marine Science - UCSB Building 520 Operational
Materials Research Lab - UCSB Building 615 Operational
Mosher Alumni House - UCSB Building 517 Operational
Multi-Activity Center - UCSB Building 511 Operational
Music - UCSB Building 531 Operational
Noble Hall - UCSB Building 544 Operational
North Hall - UCSB Building 535 Operational
Old Gym and Pool - UCSB Building 479 Operational
Orfalea Family Children's Center - UCSB Building 355 Operational
Ocean Science Education Building - UCSB Building 514 Operational
Phelps Hall - UCSB Building 560 Operational
Physical Sciences North - UCSB Building 657 Operational
Physical Sciences South - UCSB Building 672 Operational
Pollock Theater - 277 Operational
Psychology - UCSB Building 551 Operational
Psychology East - UCSB Building 251 Operational
Public Safety - UCSB Building 574 Operational
Recreation Center - UCSB Building 516 Operational
Robertson Gym - UCSB Building 533 Operational
Social Sciences & Media Studies - UCSB Building 276 Operational
South Hall - UCSB Building 528 Under Maintenance
Storke Publications - UCSB Building 589 Operational
Student Affairs & Administrative Services - UCSB Building 568 Operational
Student Health - UCSB Building 588 Operational
Student Resource Building - UCSB Building 221 Operational
Student Services - UCSB Building 599 Operational
Theater & Dance East - UCSB Building 554 Operational
Theater & Dance West - UCSB Building 223 Operational
Webb Hall - UCSB Building 526 Operational
West Campus Building 7955 Operational
Woodhouse Lab - UCSB Building 546 Operational
CAMPUS INFRASTRUCTURE Under Maintenance
Electrical Distribution Operational
Natural Gas Distribution Operational
Potable Water Distribution Operational
Sanitary Sewer Conveyance Operational
Chilled Water Loop Under Maintenance
Seawater Distribution System Operational
CBORD Operational
90 days ago
99.96 % uptime
Today
Housing.ucsb.edu website Operational
90 days ago
100.0 % uptime
Today
Kx Registration Operational
90 days ago
99.95 % uptime
Today
Lenel OnGuard (Housing) Operational
90 days ago
100.0 % uptime
Today
Mercury (RMS) Operational
90 days ago
99.84 % uptime
Today
PMWeb Operational
90 days ago
100.0 % uptime
Today
T2 Operational
90 days ago
100.0 % uptime
Today
iService Desk - WebTMA Operational
90 days ago
99.96 % uptime
Today
Metasys Operational
90 days ago
100.0 % uptime
Today
Operational
Degraded Performance
Partial Outage
Major Outage
Maintenance
Major outage
Partial outage
No downtime recorded on this day.
No data exists for this day.
had a major outage.
had a partial outage.

Scheduled Maintenance

Broida Hall Bldg. 572 - Interruption of Ventilation, Heating, Cooling and Exhaust Jun 22, 2026 21:54 - Jul 1, 2026 06:54 PDT

Update - We will be undergoing scheduled maintenance during this time.
Jun 19, 2026 - 11:50 PDT
Update - We will be undergoing scheduled maintenance during this time.
May 27, 2026 - 22:20 PDT
Update - We will be undergoing scheduled maintenance during this time.
May 27, 2026 - 22:13 PDT
Scheduled - Broida Hall Bldg. 572 - Interruption of Ventilation, Heating, Cooling and Exhaust

Date: June 22 to June 30, 2026
Time: 5AM to 2PM intermittently

FM Preventative Maintenance staff will be performing scheduled maintenance work on the building’s heating, ventilating and air conditioning (HVAC) systems. This work includes inspection and replacement of air filtration media and fan motor belts, lubrication of motors, and inspection/repair of associated ventilation and hydronic heating and cooling systems.
--------------------------------------------------------------------------------------------
PLEASE MAKE SURE ALL OCCUPANTS ARE NOTIFIED NOT TO USE FUME HOODS AND GAS CABINETS DURING OUTAGES AFFECTING THEIR AREAS.
--------------------------------------------------------------------------------------------
Monday June 22, 2026

Supply fan S-7 will be off before regularly occupied hours
Supply fan S-8 will be off before regularly occupied hours (serves 4-story offices and labs in southwest corner)
Exhaust Fan EF-3 will be off from 8:00AM - 12:00PM
--------------------------------------------------------------------------------------------
Tuesday June 23, 2026

Fume Exhaust Fan FE-1 will be off from 5:00AM - 9:00 am (serves 6-story fume hoods)
Fume Exhaust Fan FE-2 will be off from 5:00AM - 9:00 am (serves 4-story fume hoods)
--------------------------------------------------------------------------------------------
Wednesday, June 24, 2026

Supply fan S-4 will be off from 5:00AM - Noon
--------------------------------------------------------------------------------------------
Thursday June 25, 2026

Supply fan S-5 will be off from 5:00 am - Noon
--------------------------------------------------------------------------------------------
Friday June 26, 2026

Exhaust Fan EF-1 will be off from 5:00AM - 9:00AM (serves 6-story labs)
--------------------------------------------------------------------------------------------
Monday June 29, 2026

Emergency Generator will be tested from 7:30AM to 8:30AM
Equipment cool water system will be off from 8:00AM to 10:00AM
--------------------------------------------------------------------------------------------
Tuesday June 30, 2026

Supply fan S-7 will be off before regularly occupied hours (serves 6-story offices)
Air Handler AH-6 will be off from 8:00AM to 12:00PM (serves room 1219)
Compressed Air will be off from 8:00 AM to 12:00PM
--------------------------------------------------------------------------------------------
Please contact Michael Lindner, Facilities Management Preventative Maintenance Superintendent with any questions of concerns: michael.lindner@ucsb.edu.

Jun 22, 2026 - 05:00 PDT

Bldg. 589 Storke Tower - Test of Emergency Generator Jun 26, 2026 07:00-08:00 PDT

Bldg. 589 - Storke Tower- Test of Emergency Generator

Date: June 26, 2026
Time: 7:00am to 8:00am

FM Preventative Maintenance staff will be performing scheduled maintenance work & testing on the building’s Emergency Generator.

All electrical equipment connected to emergency power circuits will be momentarily affected in the brief transition to emergency power.

Please contact Michael Lindner, Facilities Management Preventative Maintenance Superintendent with any questions of concerns: michael.lindner@ucsb.edu.

Posted on Jun 24, 2026 - 07:15 PDT

Physical Sciences South Bldg. 672 - Interruption of Ventilation, Heating, Cooling and Exhaust Jul 1, 2026 05:00 - Jul 3, 2026 14:00 PDT

Physical Sciences South Bldg. 672 - Interruption of Ventilation, Heating, Cooling and Exhaust

Date: July 1 to July 3, 2026
Time: 5AM to 2PM intermittently

FM Preventative Maintenance staff will be performing scheduled maintenance work on the building’s heating, ventilating and air conditioning (HVAC) systems. This work includes inspection and replacement of air filtration media and fan motor belts, lubrication of motors, and inspection/repair of associated ventilation and hydronic heating and cooling systems.
--------------------------------------------------------------------------------------------
Wednesday July 1, 2026
Supply Fan S-2 will be off from 5:00AM to 8:00AM
--------------------------------------------------------------------------------------------
Thursday July 2, 2026
Fume Exhaust Fan FE-15 will be off from 5:00AM to 8:00AM

--------------------------------------------------------------------------------------------
Please contact Michael Lindner, Facilities Management Preventative Maintenance Superintendent with any questions of concerns: michael.lindner@ucsb.edu.

Posted on May 27, 2026 - 22:27 PDT

Chemistry Bldg. 557 - Interruption of Ventilation, Heating, Cooling and Exhaust Jul 6, 2026 05:00 - Jul 15, 2026 14:00 PDT

Chemistry Bldg. 557 - Interruption of Ventilation, Heating, Cooling and Exhaust

Date: July 6 to July 15, 2026
Time: 7AM to 4PM intermittently

FM Preventative Maintenance staff will be performing scheduled maintenance work on the building’s heating, ventilating and air conditioning (HVAC) systems. This work includes inspection and replacement of air filtration media and fan motor belts, lubrication of motors, and inspection/repair of associated ventilation and hydronic heating and cooling systems.
--------------------------------------------------------------------------------------------
PLEASE MAKE SURE ALL OCCUPANTS ARE NOTIFIED NOT TO USE FUME HOODS AND GAS CABINETS DURING OUTAGES AFFECTING THEIR AREAS.
--------------------------------------------------------------------------------------------
Monday July 6, 2026
Supply Fan S-1 will be off before normally scheduled hours
(S-1 serves first floor east of elevators)

Fume Exhaust FE-1 will be off 10:00AM to 12:00PM
(FE-1 Serves rooms 4215A, 4219, 4221, 4225, 4225A)

Fume Exhaust FE-2 will be off 12:00AM to 2:00PM
(FE-2 Serves rooms 4233,4235,4241,4241A,4243,4245,4249,4249A,4314)

--------------------------------------------------------------------------------------------
Tuesday July 7, 2026
Supply Fan S-2 will be off before normally scheduled hours
(S-2 serves second floor east of elevators)

Fume Exhaust FE-3 will be off 10:00AM to 12:00PM
(FE-3 Serves rooms 4116,4124,4126,4126A,4129,4131A,4222,4238,4238A)

Fume Exhaust FE-4 will be off 12:00PM to 2:00PM
(FE-4 Serves rooms 2201, 2205, 2209, 2211, 2215, 3201, 4021A)

--------------------------------------------------------------------------------------------
Wednesday July 8, 2026
Supply Fan S-3 will be off before normally scheduled hours
(S-3 serves third floor east of elevators)

Fume Exhaust FE-5 will be off 10:00AM to 12:00PM
(FE-5 Serves rooms 1102,2101A,2102,2104,2106,2108,3109A,3110,4110)

Fume Exhaust FE-6 will be off 12:00PM to 2:00PM
(FE-6 Serves rooms 2135,2227,2229,2230,2234,2235,3215,3219,3227)

--------------------------------------------------------------------------------------------
Thursday July 9, 2026
Supply Fan S-4 will be off before normally scheduled hours
(S-4 serves fourth floor east of elevators)

Fume Exhaust FE-7 will be off 10:00AM to 12:00PM
(FE-7 Serves rooms 2243, 2245, 2247, 2251,3 233, 3239, 3241, 3247)

Fume Exhaust FE-8 will be off 12:00PM to 2:00PM
(FE-8 Serves rooms 1135C, 1139, 1143, 1143A, 1222, 1223, 1225)

--------------------------------------------------------------------------------------------
Friday, July 9, 2026
Supply fan S-5 will be off before normally scheduled hours
(S-5 Serves floors 1 through 4, west of the elevators)

Fume Exhaust FE-9 will be off 10:00AM to 12:00PM
(FE-9 Serves rooms 3222, 3242)
Fume Exhaust FE-10 will be off 12:00PM to 2:00PM
(FE-10 Serves rooms 1126, 1132, 1132A, 2124, 2126, 3116, 3126, 3132)

--------------------------------------------------------------------------------------------
Monday July 12, 2026

Supply Fan S-6 will be off before normally scheduled hours
(S-6 serves lecture halls)

Fume Exhaust FE-11 will be off 10:00AM to 12:00PM
(FE-11 serves rooms 1056A, 1142, 1142A, 1148, 1154, 1154A, 1168, 2138, 2140, 2143, 2312A, 3138, 3142, 3146, 3150)

Fume Exhaust FE-12 will be off 12:00PM to 2:00PM
(FE-12 Serves fume hoods in rooms 2133 and 2226, general exhaust in rooms 2135, 2221, 2230A, 2234, 2317, 2251, 2319)

Compressed Air will be off from 8:00AM to 10:00AM

--------------------------------------------------------------------------------------------
Wednesday July 15th
Emergency Generator will be tested from 7:30AM to 8:30AM
Vacuum will be off 8:00AM to 12:00PM

--------------------------------------------------------------------------------------------
Please contact Michael Lindner, Facilities Management Preventative Maintenance Superintendent with any questions of concerns: michael.lindner@ucsb.edu.

Posted on Jun 23, 2026 - 20:44 PDT

Physical Sciences North Bldg. 657 - Interruption of Ventilation, Heating, Cooling and Exhaust Jul 16, 2026 05:00 - Jul 28, 2026 14:00 PDT

Update - We will be undergoing scheduled maintenance during this time.
Jun 24, 2026 - 09:31 PDT
Scheduled - Physical Sciences North Bldg. 657 - Interruption of Ventilation, Heating, Cooling and Exhaust

Date: July 16 to July 28, 2026
Time: 7:00AM to 4:00PM intermittently

FM Preventative Maintenance staff will be performing scheduled maintenance work on the building’s heating, ventilating and air conditioning (HVAC) systems. This work includes inspection and replacement of air filtration media and fan motor belts, lubrication of motors, and inspection/repair of associated ventilation and hydronic heating and cooling systems.
--------------------------------------------------------------------------------------------
PLEASE MAKE SURE ALL OCCUPANTS ARE NOTIFIED NOT TO USE FUME HOODS AND GAS CABINETS DURING OUTAGES AFFECTING THEIR AREAS.
--------------------------------------------------------------------------------------------
Thursday July 16, 2026

Supply Fan 5 will be off before normally scheduled hours
(Serves rooms 1512, 1520, 1520A, B, C, D, E, F. Also affects the welding and glass blowing area)
Fume Exhaust FE-8 will be off from 8:00AM to 12:00PM
(FE-8 Serves fume hoods in room 1520)
Fume Exhaust FE-9 will be off from 8:00AM to 12:00PM
(FE-9 serves fume hoods in rooms 1520D)

--------------------------------------------------------------------------------------------
Friday July 17, 2026
COMPRESSED AIR SYSTEM WILL BE OFF FROM 8:00AM to 12:00PM

Supply Fan 1 will be off before normally scheduled hours
(S-1 Serves rooms 1652, 1662, 1662A, 1668, 1670)
Fume Exhaust FE-1 will be off from 8:00AM to 12:00PM
(FE-1 serves rooms 1662, 1670, 2664, 2666, 3650, 3650A, 3668)
Fume Exhaust FE-2 will be off from 8:00AM to 12:00PM
(FE-2 serves rooms 1652, 2654, 3650, 3652, 4638, 4670F)

--------------------------------------------------------------------------------------------
Monday July 20, 2026

Supply Fan 2 will be off before normally scheduled hours
(S-1 Serves rooms 1641, 1642, 1642A, 1642B, 1642C, 1645, 1646, 1649, 1652)
Fume Exhaust FE-3 will be off from 8:00AM to 12:00PM
(FE-3 serves fume hoods rooms 1662, 1642, 2638, 2648, 3622A, 3636, 3637A, 3638, 3638A, 3650, 4624) (Gas Cabinets will be off for 3622A,3636,4637)
Fume Exhaust FE-6 will be off from 8:00AM to 12:00PM
(FE-6 serves fume hoods rooms 1641, 1643A, 1646, 1642B, 1649, 2537, 2647, 2653,3633RT, 3635)

--------------------------------------------------------------------------------------------
Tuesday July 21, 2026
VACUUM SYSTEM WILL BE OFF FROM 8:00AM to 12:00PM

Supply Fan 6 will be off before normally scheduled hours
(S-6 Serves rooms 4670C, 4670E, 4670G, 4668)
Fume Exhaust FE-10 will be off from 8:00AM to 12:00PM
(FE-10 serves fume hoods rooms 4670C, 4670E, 4670G, 4668)

--------------------------------------------------------------------------------------------
Wednesday July 22, 2026

EMERGENCY GENERATOR WILL BE TESTED FROM 7:30AM to 8:30AM

Supply Fan 3 will be off before normally scheduled hours
(S-3 Serves rooms 1626, 1634A, 1635A
Fume Exhaust FE-4 will be off from 8:00AM to 12:00PM
(FE-4 serves fume hoods rooms 1622, 2624, 3614, 3622)
Fume Exhaust FE-7 will be off from 8:00AM to 12:00PM
(FE-7 serves fume hoods rooms 2619,3633 LFT,3635A,4623)
(Gas cabinets will be off in 3622A, 4623, 4637)

--------------------------------------------------------------------------------------------
Thursday, July 23, 2026

EQUIPMENT COOLING SYSTEM WILL BE OFF FROM 1:00PM to 4:00PM

HVAC Supply Fan 4 will be off before normally scheduled hours
(S-4 Serves rooms 1500,1506, 1508, 1612, 1612A, 1614, 1621, 1631, 1631A, 1631B, 1631E, 1631F, 2608)
Fume Exhaust FE-5 will be from 8:00AM to 12:00PM
(FE-5 serves fume hoods rooms 1612, 2608)

--------------------------------------------------------------------------------------------
Please contact Michael Lindner, Facilities Management Preventative Maintenance Superintendent with any questions of concerns: michael.lindner@ucsb.edu.

Jun 23, 2026 - 20:55 PDT

Interfacial Lab (Chemistry Annex) Bldg. 570 - Interruption of Ventilation, Heating, Cooling and Exhaust Jul 29, 2026 05:00-14:00 PDT

Interfacial Lab (Chemistry Annex) Bldg. 570 - Interruption of Ventilation, Heating, Cooling and Exhaust

Date: July 29, 2026
Time: 5AM to 2PM intermittently

FM Preventative Maintenance staff will be performing scheduled maintenance work on the building’s heating, ventilating and air conditioning (HVAC) systems. This work includes inspection and replacement of air filtration media and fan motor belts, lubrication of motors, and inspection/repair of associated ventilation and hydronic heating and cooling systems.

--------------------------------------------------------------------------------------------
Monday July 29, 2026
Supply Fan 1 will be off before normally scheduled hours
Exhaust Fans will be off from 8:00AM to 12:00PM
FE-1 serves fume hoods
FE-2 serves gas cabinets
FE-3 serves work table

--------------------------------------------------------------------------------------------
Please contact Michael Lindner, Facilities Management Preventative Maintenance Superintendent with any questions of concerns: michael.lindner@ucsb.edu.

Posted on Jun 23, 2026 - 21:04 PDT

Engineering 2 Bldg. 503 - Interruption of Ventilation, Heating, Cooling and Exhaust Jul 30, 2026 05:00 - Aug 17, 2026 14:00 PDT

Engineering 2 Bldg. 503 - Interruption of Ventilation, Heating, Cooling and Exhaust

Date: July 30 to August 17, 2026
Time: 7AM to 4PM intermittently

FM Preventative Maintenance staff will be performing scheduled preventative maintenance work on the building’s heating, ventilating and air conditioning (HVAC) systems. This work includes inspection and replacement of air filtration media and fan motor belts, lubrication of motors, and inspection/repair of associated ventilation and hydronic heating and cooling systems.

--------------------------------------------------------------------------------------------
PLEASE MAKE SURE ALL OCCUPANTS ARE NOTIFIED NOT TO USE FUME HOODS AND GAS CABINETS DURING OUTAGES AFFECTING THEIR AREAS.

--------------------------------------------------------------------------------------------
Thursday July 30, 2026

HVAC AH –1 System will be off 5:00AM to 11:00AM
(serves interior rooms on the first, second and third floors of the southwest annex. Perimeter rooms will not be affected)

--------------------------------------------------------------------------------------------
Monday August 3, 2026

HVAC Supply Fan 1 will be off 5:00AM to 11:00AM
(serves rooms 1119A, B, C, D, E. 2111, 2119, 2120, 2122, 2122A, B, 3111, 3119, 3119A, 3120, 3122)

Fume Hood Exhaust Fan FE-1 will be off 1:00PM to 4:00PM
(serves 1117, 1119A, 1119C, 1119D, 2111, 2119, 2120, 2122, 2122A, B, 3111, 3119, 3119A, 3120, 3122)

Fume Hood Exhaust Fan FE-9 will be off 1:00PM to 4:00PM
(serves one fume hood in room 3119)

--------------------------------------------------------------------------------------------
Tuesday August 4, 2026

HVAC Supply Fan 2 will be off 5:00AM to 11:00AM
(serves 1119B, 1119E, 1119G, 1119H, 1151A, 1151B, 2133, 2134, 2145, 3133, 3134, 3146)

Fume Hood Exhaust Fan FE-2 will be off from 12:00PM to 2:00PM
(serves rooms 2133, 2134, 2119, 2120, 3122, 3133, 3134. Also serves the south end of the MOCVD Lab)

--------------------------------------------------------------------------------------------
Wednesday August 5, 2026

HVAC Supply Fan 3 will be off 5:00AM to 11:00AM
(serves 1148, 1150, 1161, 1165, 2157, 2171, 2176, 2178, 3145, 3145A, 3157, 3163, 3165, 3176, 3178)

Fume Hood Exhaust Fan FE-3 will be off from 11:00AM to 2:00PM
(serves rooms 1161, 1165, 1177, 2145, 2146, 2157, 2171, 2211, 3145, 3146, 3157, 3163, 3165. FE-3 also serves the north end of the MOCVD equipment aisle)

--------------------------------------------------------------------------------------------
Thursday August 6, 2026

HVAC Supply Fan 4 will be off 5:00AM to 11:00AM
(serves 1177, 1207, 1207A, 1208, 2211, 2218, 3177, 3211, 3217, 3218)


Fume Hood Exhaust Fan FE-4 will be off from 11:00 AM to 4:00PM
(serves 1204, 1207, 1208, 1227B, 2211, 2118, 3177, 3211, 3217, 3218)

--------------------------------------------------------------------------------------------
Friday August 7, 2026

Vacuum may be disrupted 8:00AM to 12:00PM

HVAC Supply Fan 5 will be off 5:00AM to 11:00AM
(serves 2110, 1227, 1227A, 1227B, 1227E, 1239C, 2217, 2226, 2229, 3223, 3228, 3228A)

Fume Hood Exhaust Fan FE-5 will be off from 11AM to 2:00PM
(serves rooms 1227, 1227A, 2217, 2226, 2229, 2231, 2171, 3222, 3223, 3226, 3229, 3235)

Fume Hood Exhaust Fan FE-10 will be off from 11:00AM to 2:00PM
(serves single fume hood in room 3223)

--------------------------------------------------------------------------------------------
Monday August 10, 2026

HVAC Supply Fan 6 will be off 5:00AM to 11:00AM
(serves rooms 1231, 1231A, 1237, 1239, 2231, 2235, 3228, 3229, 3236)

Fume Hood Exhaust Fan FE-6 will be off from 11:00AM to 2:00PM
(serves rooms 1231, 1239, 2232, 2235, 2331, 3235, 3236, 3229 fume hood #1)

Fume Hood Exhaust Fan FE-8 will be off from 11:00AM to 2:00PM
(serves room 1239)

Fume Hood Exhaust Fan FE-11 will be off from 11:00AM to 2:00PM
(serves room 1239C)

--------------------------------------------------------------------------------------------
Tuesday August 11, 2026

Compressed air may be disrupted between 8:30AM to 12:00PM

HVAC Supply Fan 7 will be off 5:00AM to 11:00AM
(serves 1245, 1245A, 1245B, 1245C, 1245D, 2232, 2243, 3235, 3243)

Fume Hood Exhaust Fan FE7 will be off from 1:00PM to 4:00PM
(serves rooms 1231A, 1237, 1245A, 1239, 2232, 2243, 3243)

--------------------------------------------------------------------------------------------
Wednesday August 12, 2026

Emergency Generator will be tested 7:00AM to 8:00AM
(only emergency power circuits will be briefly interrupted in transition of power and may cause interruption of Equipment cooling systems)

HVAC AHU-1 will be off 5:00AM to 11:00AM
(this fan provides supply air for Palmstrom lab 1315)

Exhaust Fan EF-1 will be off from 11:00AM to 2:00PM
(this fan provides exhaust and fume hood exhaust for Palmstrom lab 1315)

--------------------------------------------------------------------------------------------
Thursday August 13, 2026

HVAC AHU-4A will be off 5:00AM to 8:00AM
(this fan provides half the supply air for the MOCVD Lab)

HVAC AHU-4B will be off 8:00AM to 11:00AM
(this fan provides half the supply air for the MOCVD Lab.)

Fume Exhaust Fan FE-1A will be off 11:00 AM to 2:00PM
(serving room 3229 fume hoods and snorkels)

--------------------------------------------------------------------------------------------
Friday August 14, 2026

HVAC AHU – 5A will be off 5:00AM to 8:00AM
(serves the Teaching Clean Room)

Exhaust Fan EF-1A will be off from 11:00AM to 2:00PM
(serves the Teaching Clean Room, the center section of the MOCVD Lab, and the south end of the MOCVD equipment aisle)

Exhaust Fan EF-2A will be off from 11:00AM to 2:00PM
(serves the Teaching Clean Room and the north end of the MOCVD Lab)

--------------------------------------------------------------------------------------------
Saturday August 15, 2026

Date reserved for service of equipment in 3426 serving lab (Recharge Work)
AHU-1
FC-2

--------------------------------------------------------------------------------------------
Please contact Michael Lindner, Facilities Management Preventative Maintenance Superintendent with any questions of concerns: michael.lindner@ucsb.edu.

Posted on Jun 23, 2026 - 21:24 PDT

Engineering Science Bldg. 225 - Interruption of Ventilation, Heating, Cooling and Exhaust Aug 18, 2026 05:00 - Aug 21, 2026 14:00 PDT

Engineering Science Bldg. 225 - Interruption of Ventilation, Heating, Cooling and Exhaust

Date: August 18 to August 21, 2026
Time: 5AM to 2PM intermittently

FM Preventative Maintenance staff will be performing scheduled preventative maintenance work on the building’s heating, ventilating and air conditioning (HVAC) systems. This work includes inspection and replacement of air filtration media and fan motor belts, lubrication of motors, and inspection/repair of associated ventilation and hydronic heating and cooling systems.

--------------------------------------------------------------------------------------------
PLEASE MAKE SURE ALL OCCUPANTS ARE NOTIFIED NOT TO USE FUME HOODS AND GAS CABINETS DURING OUTAGES AFFECTING THEIR AREAS.

--------------------------------------------------------------------------------------------
Tuesday August 18, 2026

Supply Fan AH-1 will be off before normally scheduled hours
(serves labs on second and third floor north)

--------------------------------------------------------------------------------------------
Wednesday August 19, 2026
Emergency Generator will be tested from 7:00AM to 8:00AM
(generator tests will affect emergency circuits throughout the building. Emergency circuits will lose power briefly during the test - less than one minute while switching to the generator)

Supply Fan AH-2 will be off before normally scheduled hours
(serves Labs on second and third floor south)

--------------------------------------------------------------------------------------------
Thursday August 20, 2026

Exhaust Fans EF-1 & EF-2 will be off from 8:00AM to 12:00PM
(serves Labs and fume hoods on the second and third floor)

Compressed Air for general lab air will be off line 8:00AM to 9:00AM
--------------------------------------------------------------------------------------------

Please contact Michael Lindner, Facilities Management Preventative Maintenance Superintendent with any questions of concerns: michael.lindner@ucsb.edu.

Posted on Jun 23, 2026 - 21:34 PDT
Jun 25, 2026

No incidents reported today.

Jun 24, 2026

No incidents reported.

Jun 23, 2026

No incidents reported.

Jun 22, 2026
Completed - The scheduled maintenance has been completed.
Jun 22, 17:00 PDT
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jun 22, 06:00 PDT
Scheduled - We will be undergoing scheduled construction activities along UCen Road at this time. Work will include crane lift behind the library. The loading dock area will be taken over by the crane setup, and will not be accessible for deliveries or the public. Parking will also be limited in the vicinity. Impacts include slower traffic in the area.
Jun 18, 12:57 PDT
Jun 21, 2026

No incidents reported.

Jun 20, 2026
Resolved - This incident has been resolved.
Jun 20, 12:44 PDT
Investigating - Service Outage Notification
Jun 20, 12:34 PDT
Resolved - This incident has been resolved.
Jun 20, 12:44 PDT
Investigating - Service Outage Notification
Jun 20, 12:33 PDT
Jun 19, 2026

No incidents reported.

Jun 18, 2026
Completed - The scheduled maintenance has been completed.
Jun 18, 12:00 PDT
Update - We will be undergoing scheduled maintenance during this time.
May 27, 21:53 PDT
Scheduled - Interactive Learning Pavilion Bldg. 506 - Interruption of Ventilation, Heating, Cooling and Exhaust

Date: June 12 to June 18, 2026
Time: 5AM to 2PM intermittently

FM Preventative Maintenance staff will be performing scheduled preventative maintenance work on the building’s heating, ventilating and air conditioning (HVAC) systems. This work includes inspection and replacement of air filtration media and fan motor belts, lubrication of motors, and inspection/repair of associated ventilation and hydronic heating and cooling systems.

--------------------------------------------------------------------------------------------
Wednesday 17th, 2026
Emergency Generator will be tested from 6:30AM to 7:30AM
--------------------------------------------------------------------------------------------
Please contact Michael Lindner, Facilities Management Preventative Maintenance Superintendent with any questions of concerns: michael.lindner@ucsb.edu.

May 27, 21:52 PDT
Jun 17, 2026
Jun 16, 2026

No incidents reported.

Jun 15, 2026

Unresolved incident: Davidson Library Bldg. 525 - Construction and Temporary Shutdown of Cooling System.

Jun 14, 2026

No incidents reported.

Jun 13, 2026
Completed - The scheduled maintenance has been completed.
Jun 13, 13:00 PDT
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jun 13, 05:00 PDT
Scheduled - Fume hood and general exhaust fans for Marine Science (Bldg. 520) will be off on Saturday June 13, 2026 from 5:00AM to 2:00 PM while Facilities Management (FM) performs maintenance on the system. This work will affect the system that serves all labs.

If you have any questions or concerns, please contact Mike Lindner, FM Sr. Superintendent for Preventative Maintenance, at 805-319-6624.

Jun 12, 13:11 PDT
Jun 12, 2026

Unresolved incident: Life Sciences, 235; Psychology, 551; Psychology East, 251 – East Campus Student Housing Project.

Jun 11, 2026
Completed - The scheduled maintenance has been completed.
Jun 11, 14:00 PDT
Update - We will be undergoing scheduled maintenance during this time.
Jun 4, 06:18 PDT
Update - We will be undergoing scheduled maintenance during this time.
May 29, 08:37 PDT
Scheduled - Bio Engineering Bldg. 512 - Interruption of Ventilation, Heating, Cooling and Exhaust


Date: June 4 to June 11, 2026
Time: 5:00AM to 2:00PM intermittently

FM Preventative Maintenance staff will be performing scheduled preventative maintenance work on the building’s heating, ventilating and air conditioning (HVAC) systems. This work includes inspection and replacement of air filtration media and fan motor belts, lubrication of motors, and inspection/repair of associated ventilation and hydronic heating and cooling systems.

Thursday June 4, 2026
AHU-1 will be off 5am to 9:00 am
EF-9 will be down 5:00am to 9:00 am (Serves Cage Wash Dirty Side 0304 & Clean Side 0505)
EF-12 will be off 5:00am to 9:00 am (Serves Cage Washer & 0302 BSC C1)
EF-1 will be off 9 am to Noon
EF-2 will be off 9am to Noon
Vacuum system will be serviced from 8:00AM – 12:00PM
--------------------------------------------------------------------------------------------
Friday June 5, 2026
EF-8 will be down from 5am to 9am (Serves Loading Dock 1309)
EF-11 will be down from 5am to 9 am
Compressed Air system will be serviced from 8:00AM – 12:00PM
--------------------------------------------------------------------------------------------
Wednesday June 10, 2026

Emergency Generator will be tested from 7:30AM – 8:30AM
Backup Chiller will be tested from 7:30AM to 8:30AM
--------------------------------------------------------------------------------------------
Please contact Michael Lindner, Facilities Management Preventative Maintenance Superintendent with any questions of concerns: michael.lindner@ucsb.edu.

May 27, 21:40 PDT
Resolved - This incident has been resolved.
Jun 11, 11:32 PDT
Investigating - Service Outage Notification
Jun 11, 11:02 PDT
Completed - The scheduled maintenance has been completed.
Jun 11, 10:00 PDT
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jun 11, 08:00 PDT
Scheduled - We will be undergoing modifications of the fire sprinkler system underneath the Ocean Side of the library. This will include draining the system and putting the fire alarm on test. No impact is anticipated.
Jun 10, 08:18 PDT
Resolved - This incident has been resolved.
Jun 11, 00:49 PDT
Investigating - Service Outage Notification
Jun 11, 00:45 PDT